Monday, July 25, 2011

Shower Floor

This is the "extra" bathroom -- all the red stuff will be covered in tile. The red stuff is a painted on rubber type of stuff to help waterproof underneath the tiles - Isn't this a cool shower floor?

One Bathroom almost tiled!

Oldest Daughter's bathroom has all tile in place except for a few cut ones in the back corner on the right. That little area will be a cabinet for storage of towels, etc.

Monday, July 11, 2011

Front Door (foyer) Tiled "Rug" area



This area will be covered in hardwood so we designed this tile "rug" area by the front door so we won't have to ever worry about a wet rug on the wood floor. 12 inch tiles on the diagonal with 2 inch mosaic tiles on the border. The 12 inch tiles are cemented in, but the mosaic ones aren't permanently set yet. I'm pretty excited about this project!
Starting the 6 inch tiles above the glass mosaic in the first bathroom (Left Photo) -- getting up to the glass mosaic in the second bathroom (Right Photo)

Sunday, July 10, 2011

Day 3 tile

Up to the glass mosaic in one kid's shower, and the first triangle of tiles is done on the other kid's. You can see two cutouts of tile on the one that is more finished -- one for a corner shelf and the other for the soap dish...it's got details!!!

Saturday, July 9, 2011

Day 2 - Tile


Update of about 4 more hours put into that shower...just wait till you see what we do this afternoon -- it will be a surprise!

Friday, July 8, 2011

Tile Job - Day 1

Older daughter's shower...first day of tiling.

Wednesday, June 29, 2011

Lights at Night



Here's how it looks with the porch lights on at night...
We have additional flood lights on the corners, but they're not turned on in this picture.

Sunday, June 26, 2011

Tile & Wood Samples


We've decided on this wood & tile. Kitchen will be a pattern with the 18" tiles and some 6" ones from the same line. The showers will have the 2" mosaic on the floors, 6 or 12" ones on the walls, and the little glass tiles as an accent about eye level. The wood is an engineered maple with distress signs so they won't look "too perfect" -- Also took this picture in the kitchen so you could see how the walls look with this flooring.

Monday, June 13, 2011

Power Soon!

All the lighting is installed.
Outlets and switches all wired.
All electrical panels wired.
Electrical Inspection passed.

Co-op has us scheduled to turn on the power on this WEDNESDAY!!!