Wednesday, June 29, 2011
Lights at Night
Here's how it looks with the porch lights on at night...
We have additional flood lights on the corners, but they're not turned on in this picture.
Sunday, June 26, 2011
Tile & Wood Samples
We've decided on this wood & tile. Kitchen will be a pattern with the 18" tiles and some 6" ones from the same line. The showers will have the 2" mosaic on the floors, 6 or 12" ones on the walls, and the little glass tiles as an accent about eye level. The wood is an engineered maple with distress signs so they won't look "too perfect" -- Also took this picture in the kitchen so you could see how the walls look with this flooring.
Monday, June 13, 2011
Power Soon!
All the lighting is installed.
Outlets and switches all wired.
All electrical panels wired.
Electrical Inspection passed.
Co-op has us scheduled to turn on the power on this WEDNESDAY!!!
Outlets and switches all wired.
All electrical panels wired.
Electrical Inspection passed.
Co-op has us scheduled to turn on the power on this WEDNESDAY!!!
Flooring Choices
Some of the "narrowed down" choices for flooring:
Engineered hardwood for most of the house:
Shaw: Rosedown Hickory: Smokehouse Spice color: 5” planks with LOTS of variation
Two tile choices (bathrooms & kitchen floor)
Marazzi Campione: Armstrong color : up to 20 x 20 tiles
Or
Marazzi Artea Stone: Cappucino color : up to 20 x 20 tiles
Tuesday, June 7, 2011
Outside Lighting almost finished
Sunday, June 5, 2011
Electrical
Applied for electrical service this week -- should have power in about 2 weeks (This is my own estimate and is based on no knowledge of how electrical service works!)